ISASTUR
  • ES
  • EN
  • FR

Navigation

  • ISASTUR
  • The group
  • Companies
  • News
  • Where we are
  • Contact
  • Blog
  • Jobs
  • Corporate catalogs

Sectors

  • Water
  • Automotive
  • Energy
  • Mining
  • Naval
  • Petrochemical
  • Chemical
  • Renewable
  • Siderurgy / Metallurgy

Activities

  • Electricity and instrumentation
  • EPC / Turnkey
  • Facility Management
  • Engineering
  • Lines
  • Maintenance
  • Mechanical Assembly
  • Substations

automotive

chemical

energy

mining

naval

petrochemical

renewable

siderurgy/metallurgy

water

energía

Cardif Energy From Waste Plant - United Kingdom

Cardif Energy From Waste Plant

Client: CNIM
Location: Cardiff (United Kingdom)

Ciclo Combinado Koudiet 1200 MW - Algerie

Ciclo Combinado Koudiet 1200 MW Ciclo Combinado Koudiet 1200 MW Ciclo Combinado Koudiet 1200 MW

Client: IBERDROLA
Location: Algerie

Mantenimiento Anual Ciclo Combinado Alpiq - Spain

Mantenimiento Anual Ciclo Combinado Alpiq

Client: ALPIQ ENERGÍA ESPAÑA, S.A.U
Location: Tarragona (Spain)

Montaje mecánico Ciclo Combinado Bouchain - 575 MW - France

Montaje mecánico Ciclo Combinado Bouchain - 575 MW Montaje mecánico Ciclo Combinado Bouchain - 575 MW

Client: GENERAL ELECTRIC
Location: France

PEM / Commissioning Ciclo Combinado Bouchain - 575 MW - France

PEM / Commissioning Ciclo Combinado Bouchain - 575 MW PEM / Commissioning Ciclo Combinado Bouchain - 575 MW

Client: GENERAL ELECTRIC
Location: France

Ciclo Combinado Brigadier López - 420 MW - Argentina

Ciclo Combinado Brigadier López - 420 MW

Client: UTE ISOLUX-IECSA
Location: Santa Fé (Argentina)

Central de Ciclo combinado con una potencia total de 420 MW. Los trabajos consisten en la ejecución del montaje de una caldera HRSG, de flujo horizontal de 3 presiones con recalentado.

Ciclo Combinado Lichterferlde - 230 MW - Germany

Ciclo Combinado Lichterferlde - 230 MW Ciclo Combinado Lichterferlde - 230 MW Ciclo Combinado Lichterferlde - 230 MW

Client: IBERDROLA
Location: Germany

Planta Cogeneración ENAP Aconcagua - Chile

Planta Cogeneración ENAP Aconcagua Planta Cogeneración ENAP Aconcagua

Client: DURO FELGUERA - OPEMASA
Location: Chile

Mechanical assembly of the UTE BESÓS 850 MW combined cycle power plant - Spain

Mechanical assembly of the UTE BESÓS 850 MW combined cycle power plant

Client: UTE BESOS 5 (TECNICAS REUNIDAS-DURO FELGUERA)
Location: Spain

Mechanical assembly of the UTE BESÓS - 850 MW combined cycle power plant, including: 1. (2) HRSG NEM boilers. 2) Smokestack. 3) Comprehensive piping.

Revamping/Reparaciones/Parada Planta Glefaran - Mejoras sistema combustión y emisiones en caldera de biomasa - Spain

Client: GLEFARAN
Location: Aranguren (Spain)

Automation

Control system of auxiliary services at cogeneration plant - Spain

Control system of auxiliary services at cogeneration plant

Client: CERANOR
Location: Spain

Control system of auxiliary services for Phase 1 and 2 of the CERANOR Don Juan cogeneration plants in Valencia, including connection with the PLC control systems of the groups to display all statuses/controls on screen. SIEMENS PLC-based system and SCADA INTOUCH system.

Configuration and commissioning of microscada and ref systems at distribution centres - Spain

Configuration and commissioning of microscada and ref systems at distribution centres

Client: HIDROELECTRICA DEL CANTABRICO
Location: Spain

Development of systems to perform monitoring and control of substations and transmission centres. The ABB scada system was used: MicroSCADA. Enables remote control with interlocks and connections with field units and control and protection units through various communication protocols. At the same time, microscada systems communicate with the office to ensure centralised control.

Control system at hydropower plants - Spain

Control system at hydropower plants

Client: ENDESA
Location: Spain

Updating throughout the years of the control systems of several hydropower plants and installing S7-400 programmable automation, SIEMENS SCADA WinCC and PROFIBUS networked remote control system. Plants covered by the works: EUME, PRADA, SAN SEBASTIAN, BARCENA, LAS ONDINAS, CORNATEL, QUEREÑO.

Electricity and instrumentation

Andina thermal electric power plant - Chile

Andina thermal electric power plant

Client: COBRA PLANTAS INDUSTRIALES
Location: Chile

Assembly and start-up of electrical and instrumentation facilities and the design, supply and assembly of the lighting facility for Units I and II in Mejillones.

Substation at Tierra Amarilla simple cycle power plant - Chile

Substation at Tierra Amarilla simple cycle power plant

Client: DURO FELGUERA
Location: Chile

Turnkey construction project including engineering, supply, assembly and start-up of the 220kV substation.

Dock Sud combined cycle power plant - Argentina

Dock Sud combined cycle power plant

Client: UTE BABCOCK WILCOX/ABB ALSTOM POWER
Location: Argentina

Assembly of electrical facilities and instrumentation.

Caruachi hydropower plant - Venezuela

Caruachi hydropower plant

Client: CONSORCIO DRAVICA
Location: Venezuela

Electrical system assembly, testing and start-up.

Montoir combined cycle plant - France

Montoir combined cycle plant

Client: TECNICAS REUNIDAS
Location: France

Electrical and instrumentation facilities for Gaz de France's Montoir combined cycle plant.

Compressor stations for Magreb-Europe gas pipeline - Morocco

Client: INITEC/TECNICAS REUNIDAS
Location: Morocco

Supply and electrical and instrumentation assembly.

Engineering

Palos 400/220 kV substation - Spain

Palos 400/220 kV substation Palos 400/220 kV substation

Client: RED ELECTRICA DE ESPAÑA (REE)
Location: Spain

Comprehensive engineering works for the construction of the Palos 400 kV substation, with exterior, ring-configured armoured modules with two bays, three combined-cycle group terminals and one 400/220 kV autotransformer. Included in the works performed was the design and calculation of earth-moving, civil works, structures, installations, control and protection and auxiliary services, for both the documentation required for legal processing and for the tender and subsequent construction of the substation.

Jordana 400/220 kV substation - Spain

Jordana 400/220 kV substation

Client: SIEMENS
Location: Spain

Comprehensive engineering works for the construction of the Jordana 400/220 kV substation. With a 400 kV compound, with exterior, ring-configured armoured modules with two bays and one 400/220 kV autotransformer. And a 220 kV compound, with interior, double busbar-configured armoured modules with seven bays, one autotransformer bay and coupling. Included in the works performed was the design and calculation of earth-moving, civil works, structures, installations, control and protection and auxiliary services, for both the documentation required for legal processing and for the tender and subsequent construction of the substation.

Fuendetodos 400 kV substation - Spain

Fuendetodos 400 kV substation

Client: RED ELECTRICA DE ESPAÑA (REE)
Location: Spain

Comprehensive engineering works for the construction of the Fuendetodos 400 kV substation, with exterior, ring-configured armoured modules, two bays and one autotransformer. Included in the works performed was the design and calculation of earth-moving, civil works, structures, installations, control and protection and auxiliary services, for both the documentation required for legal processing and for the tender and subsequent construction of the substation.

Sant Adriá de Besós 220/66/25 kV substation - Spain

Sant Adriá de Besós 220/66/25 kV substation

Client: ENDESA DISTRIBUCION ELECTRICA, S.A.
Location: Spain

Comprehensive engineering works for the construction of the Sant Adriá de Besós 220 kV substation, with interior, double busbar-configured armoured modules with five bays and four transformer bays, three group bays, two longitudinal coupling bays and one cross coupling. Included in the works performed was the design and calculation of earth-moving, civil works, structures, installations, control and protection and auxiliary services, for both the documentation required for legal processing and for the tender and subsequent construction of the substation.

Puerto de la Cruz 400 kV substation - Spain

Puerto de la Cruz 400 kV substation

Client: RED ELECTRICA DE ESPAÑA (REE)
Location: Spain

Comprehensive engineering works for the construction of the Puerto de la Cruz 400 kV substation, with conventional switchgear, an interrupter and half configuration made up of four lanes, including two reactor bays and one 400/220 kV autotransformer. Included in the works performed was the design and calculation of earth-moving, civil works, structures, installations, control and protection and auxiliary services, for both the documentation required for legal processing and for the tender and subsequent construction of the substation.

Morvedre 400kV substation - Spain

Morvedre 400kV substation

Client: RED ELECTRICA DE ESPAÑA (REE)
Location: Spain

Comprehensive engineering works for the construction of the Morvedre 400 kV substation, with exterior, double busbar ring-configured armoured modules with two bays, three combined-cycle group terminals and one 400/220 kV autotransformer and two bays to the converter station (connection cable with the Balearic Islands). Included in the works performed was the design and calculation of earth-moving, civil works, structures, installations, control and protection and auxiliary services, for both the documentation required for legal processing and for the tender and subsequent construction of the substation.

Asset Integration Project - Spain

Asset Integration Project

Client: RED ELECTRICA DE ESPAÑA (REE)
Location: Spain

Comprehensive engineering works, including documentation on the tender and subsequent construction of the facilities, for more than 50 facilities across Spain as part of REE's asset integration project. Including both the documentation on the structure and assembly of switchgear to be refurbished and the engineering to remodel the control, protection and remote control equipment. Partial technical assistance in critical phases.

Puentes 400 kV substation - Spain

Puentes 400 kV substation

Client: SIEMENS
Location: Spain

Comprehensive engineering works for the construction of the Puentes 400 kV substation, with interior, double busbar-configured technology made up by three group terminals and one coupling. Included in the works performed was the design and calculation of earth-moving, civil works, structures, installations, control and protection and auxiliary services, for both the documentation required for legal processing and for the tender and subsequent construction of the substation.

Galapagar 220 kV substation - Spain

Galapagar 220 kV substation

Client: RED ELECTRICA DE ESPAÑA (REE)
Location: Spain

Comprehensive engineering works for the construction of the Galapagar 220 kV substation, with conventional switchgear, double busbar configuration, two bays, one coupling bay and two transformer bays. Included in the works performed was the design and calculation of earth-moving, civil works, structures, installations, control and protection and auxiliary services, for both the documentation required for legal processing and for the tender and subsequent construction of the substation.

Subestaciones San Gil y Peña II 30/132 kV - Spain

Client: ENEL UNION FENOSA RENOVABLES
Location: Spain

Diseño del esquema protectivo, Ajuste de selectividades, Pruebas de Protecciones, Pruebas Funcionales y Asistencia a las Puestas en Servicio de las subestaciones eléctricas de SAN GIL y PEñA II 30/132 kV.

Ingeniería de Detalle

SUBESTACIÓN JORDANA - 400/220 kV - Spain

Client: RED ELECTRICA DE ESPAÑA (REE)
Location: Casares, Málaga (Spain)

Lines

Línea 220 kV TOLCHÉN - Chile

Línea 220 kV TOLCHÉN Línea 220 kV TOLCHÉN Línea 220 kV TOLCHÉN

Client: ACCIONA ENERGIA
Location: Mulchén, Región Bio Bío (Chile)

Construcción de la línea eléctrica de 220 kV con una longitud de 33 km en dos tramos entre las subestaciones de los parques eólicos de San Gabriel y Tolpan y la subestación de Mulchen, en Renaico, Chile.

Línea 220 KV Lagunas-Crucero en la subestación María Elena - Chile

Línea 220 KV Lagunas-Crucero en la subestación María Elena Línea 220 KV Lagunas-Crucero en la subestación María Elena Línea 220 KV Lagunas-Crucero en la subestación María Elena

Client: GENERACIÓN SOLAR SPA
Location: Región de Antofagasta (Chile)

Ingeniería, suministro, construcción, montaje, pruebas y puesta en servicio y operación del Seccionamiento del circuito 2 de la LAT Cruceros - Laguna 220 kV y su conexión en la SE María Elena.

132 kV Aguilar de Campo-La Lora transmission line - Spain

132 kV Aguilar de Campo-La Lora transmission line

Client: COBRA INSTALACIONES Y SERVICIOS, S.A.
Location: Spain

Length of hanging: 21km LA-380 single circuit (GULL) plus OPGW optical fibre cable. Hoisting and reinforcement of Arce supports.

132kV overhead line from Mendoza to Boulogne Sur Mer - Argentina

Client: EDEMSA
Location: Argentina

Construction and start-up of a 32 km-long 132kV overhead line.

Maintenance

Substation maintenance - Spain

Substation maintenance

Client: HIDROCANTABRICO DISTRIBUCION ELECTRICA, S.A.
Location: Spain

Maintenance of 50 to 400 kV substations in Asturias between 2005 and 2011.

Works and services at substations - Spain

Works and services at substations

Client: E.ON DISTRIBUCION, S.L
Location: Spain

Works and services at E.ON substations in Asturias and Lugo from 2010 to 2013.

Mantenimiento red de media y baja tensión en Ferrol (A Coruña) - Spain

Client: UFD
Location: España (Spain)

Los Trabajos en la red de media y baja tensión de UFD en Ferrol consisten en las siguientes tareas:

·         Trabajos de montaje e instalación de acometidas.

·         Nuevos suministros o ampliación de los existentes.

·         Revisión de las instalaciones de enlace.

·         Modificaciones de la red.

·         Trabajos de desarrollo de la red de media y baja tensión.

·         Trabajos de adecuación, sustitución o reforma y reglamentación de instalaciones.

·         Puntos de telecontrol.

·         Trabajos para el mantenimiento en las instalaciones de la red de media y baja tensión.

·         La Operación Local, que abarca las actividades de:

o  Maniobra de la red de media y baja tensión.

o  Localizar, aislar averías y reponer el servicio de forma provisional en la red de media y baja tensión.

Atención de avisos por posibles averías en las instalaciones particulares de los clientes en baja tensión (denominados Suministros Únicos) y su reparación si el cliente acepta los precios y así lo solicita.

Trabajos de mantenimiento y reformas en subestaciones - Spain

Client: EDP RENOVABLES ESPAÑA, S.L.U.
Location: España (Spain)

Las obras y servicios que se llevan a cabo en las Subestaciones ≥ 50kV de EDP HC Energía constan principalmente de las siguientes tareas:

 

  • Reformas, renovaciones y ampliaciones
  • Ingeniería: estudios Previos Técnico-económicos, documentación para tramitación administrativa, documentos de licitación de obras, actualización de planos y otros servicios.
  • Mantenimiento Planificado (Preventivo y Predictivo).
  • Mantenimiento Correctivo.
  • Adecuaciones de las instalaciones derivadas  de las inspecciones reglamentarias.
  • Servicio de Retén para atención de averías.

 

Substations

Electrical and mechanical assembly of the Soto de Ribera 400 kV substation - Spain

Electrical and mechanical assembly of the Soto de Ribera 400 kV substation

Client: HIDROELECTRICA DEL CANTABRICO
Location: Spain

Expansion of the 400 kV compound of the Soto de Ribera (Ferreros) substation, including the engineering, supply, electrical and mechanical assembly and civil works of two 400 kV lanes called Calle 5 and Calle 6, including the supply to and installation of the necessary control, protection and communications housings. This 400 kV compound has an interrupter and a half configuration in a conventional weatherproof plant. In addition, the supply to, assembly of and civil works were carried out for the gateway of two 400 kV transmission lines to carry out the 400kV overhead-to-underground transition.

Subestación 220 kV Capricornio - Chile

Subestación 220 kV Capricornio Subestación 220 kV Capricornio Subestación 220 kV Capricornio

Client: ENGIE ENERGÍA S.A.
Location: Antofagasta (Chile)

Desarrollo de la ingeniería básica y detalle, suministro, construcción, montaje, pruebas y puesta en servicio de todos los trabajos asociados al nuevo patio de 220 kV de la Subestación Capricornio.

"Turnkey" construction of the Telledo GIS 220 kV substation - Spain

Client: RED ELECTRICA DE ESPAÑA (REE)
Location: Spain

"Turnkey" construction of the GIS Telledo 220 kV substation in accordance with REE standards, including: engineering, civil works, building construction, electrical and mechanical assembly, exterior switchgear supply and protection housing, auxiliary services, cabling and final testing up to commissioning for REE. The substation includes two bays, two transformer and coupling bays executed as armoured GIS manufactured by Siemens.

Subestación 220 kV Alto Melipilla - Chile

Subestación 220 kV Alto Melipilla Subestación 220 kV Alto Melipilla

Client: CHILQUINTA ENERGIA
Location: Provincia Melipilla. Región Metropolitana (Chile)

Las obras contemplan el cambio de configuración del patio de 220 kV a interruptor y medio, instalación de un nuevo banco de autotransformadores monofásicos 220/110 kV 150 MVA con sus respectivos paños de conexión, en ambos niveles de tensión y la ampliación de la barra de 110 kV incluyendo la instalación de un paño seccionador en esta última barra.

San Cibrao 20/132 kV substation - Spain

San Cibrao 20/132 kV substation

Client: E.ON DISTRIBUCION, S.L
Location: Spain

Design of protective outline, adjustment of selectivity, protection testing, functional testing and start-up assistance for the SAN CIBRAO 20/132 kV electrical substation.

400 kV Electromechanical assembly rooms substation - Spain

400 kV Electromechanical assembly rooms substation

Client: RED ELECTRICA DE ESPAÑA (REE)
Location: Spain

Electromechanical installation and commissioning of 400 kV substation Salas (Asturias) for REE. The substation configuration is switch and Environment, with three streets, and the following positions:

  • 4 position 400 kV line.
  • 1 output at 400 kV transformer to a 400/132 kV, owned by HC Energy.